What We Have Done so Far Cumulative Shots Since Start of Project
0.1 J fusion yield 300
1.8 billion C temperature 1,000
Switches firing together 1,200
Identified impurity problem 1,500
Design of monolithic tungsten electrodes as impurity solution 1,800
Identification of runaway electron problem, solutions 1,900
Identification of oxygen problem, solutions 1,930
0.25 J fusion yield 2,090
2.8 billion C temperature 2,140
 

Since Start of FF-2B

 
Development Tasks and Milestones Cumulative Shots from Present Time Achieved
1. Demonstrate achievement of low impurity 100 ACHIEVED ✓ 75 shots
2. Demonstrate 10 J Fusion yield 200
3. Demonstrate continued scaling of yield with current 300
4. Demonstrate 100-fold increase of density 400
5. Install and test heating and other equipment for hydrogen-boron fuel 500
6. Test increased current with upgrade of power supply 600
7. Tests with hydrogen-boron partial gas 700
8. Demonstrate 100 J fusion yield with hydrogen-boron 800
9. Demonstrate 1,000 J fusion yield 900
10. Tests with pure hydrogen-boron fuel 1,000
11. Demonstrate scientific feasibility, net energy output 1,300

UPDATES

VIDEOS

pp

PHOTOS

p

PODCAST

ppp

BOOKS

p

PRESENTATIONS

p

FUND FUSION

Wefunder Logo p LPPFusion Logo


PROGRESS REPORTS

* indicates required

Please select all the ways you would like to hear from LPPFusion:

You can unsubscribe at any time by clicking the link in the footer of our emails. For information about our privacy practices, please visit our website.

We use Mailchimp as our marketing platform. By clicking below to subscribe, you acknowledge that your information will be transferred to Mailchimp for processing. Learn more about Mailchimp's privacy practices here.

You have Successfully Subscribed!

Share This